✔ Communication Protocol

What is IEC 60870-5-104? The standard remote monitoring and control protocol of the energy sector

IEC 60870-5-104 (104 for short) is the international standard protocol used between power plants, substations, RTUs and control centres.

Its serial counterpart is IEC 60870-5-101; 104 carries the same message structure over TCP/IP. In Turkey it is widely used to connect power plants and substations to load dispatch centres and SCADA systems.

Highlights

  • TCP/IP
  • TCP 2404
  • Event-based reporting
  • Millisecond time stamps
  • Select-before-operate

How does it work?

The central system acts as the client (master), and the field RTU or gateway as the server (slave). Each signal has an IOA (information object address); breaker positions, measurements and commands are identified by this number.

Once connected, the centre requests all values at once with a general interrogation (GI). After that, the field sends only changed values, with time stamps. Commands are given safely using select-before-operate.

Hardware architecture

Relay / Analyser / I/OfieldRTU / Gateway104 serverRouter + FirewallVPNFibre / MPLS / 4GlinkSCADA / Load Dispatch104 client
  • RTU or station gateway: Collects data from relays, analysers and I/O, and serves it to the centre via 104.
  • GPS time server: Needed for correct event times.
  • Redundant connection: Critical sites use two separate links (e.g. fibre + 4G) and two separate centre connections.
  • Firewall and VPN: 104 itself has no encryption, so the connection should run inside a VPN.

Cable and material selection

  • Inside the substation: Fibre optic is preferred; it is immune to electromagnetic noise and ground potential differences in high-voltage environments.
  • Inside panels: Shielded Cat6 cable and industrial switches.
  • Remote link: Fibre or MPLS where possible; otherwise an industrial 4G router (external antenna, dual SIM if possible).
  • Power: Communication equipment should run on battery-backed DC so that communication continues when the grid goes down; that is exactly when information is needed most.
  • Serial (101) lines: Shielded twisted-pair cable for RS-485/RS-232 and surge protectors.

Advantages and disadvantages

Advantages

  • Widely accepted international standard in the energy sector
  • Event-based reporting with millisecond time stamps
  • Safe commands (select-before-operate)
  • Redundant connection and reconnection support
  • Interoperability between vendors' devices

Disadvantages

  • No encryption in the protocol; VPN or IEC 62351 is needed
  • IOA and data type mapping needs care
  • Small interpretation differences between vendors can slow integration
  • Needs more expertise than Modbus

104 compared with similar protocols

IEC 104 vs IEC 101

IEC 104IEC 101
MediumTCP/IP (Ethernet, fibre, 4G)Serial (RS-232/485, modem)
DistanceNetwork-based, practically unlimitedLimited by serial line and modem
SpeedHighLow
UseMost new projectsOlder and serial-linked sites

IEC 104 vs Modbus TCP

IEC 104Modbus TCP
Time stampsOn every eventNone
ReportingOn changeConstant polling
Command safetySelect-before-operateDirect write
Best forEnergy, substations, data to authoritiesField devices, analysers

How to test it

  1. Agree common address (ASDU), IOA list, data types and timing parameters (t1, t2, t3, k, w) with the other side.
  2. Check access to the IP address and port 2404.
  3. Once connected, run a general interrogation and confirm all IOAs arrive with the correct type.
  4. Make a change in the field and verify the event arrives with the correct time stamp.
  5. Test commands in select-then-execute order, with authorised staff on site.

Testing with ATLAS SCADA

You can set up the 104 connection with ATLAS SCADA and test signals, measurements and commands. Incoming events can be watched with their time stamps on screen and in the event list.

Let's review your project together

Let's work out together which architecture, hardware and cabling fit your facility.

Let's talk about your project